Power Shutdown

Srinagar, Jan 25: According to the Chief Engineer, Distribution, KPDCL, in order to carry out erection of poles for Sangam-I Line, the shutdown of 33KV Awantipora-Sangam Line-I shall be observed due to which 33/11KV Receiving Stations at Mirhama, Sangam & Khellan shall remain off while power supply to the Rakh Litter, Naina, Batapora, Khella, Medhama, Khiram and Sangam areas will be affected from 11:00 AM to 04:00 PM on 29 January, 2025.

Also, the shutdown of 33KV Awantipora-Sangam Line-II shall be observed due to which 33/11KV Receiving Stations at K-koot, Panzgam and LIS Tral shall remain off while power supply to the Saimoh, K-koot, Hariparigam, Kaigam, Chakoora, Gulzarpora, Panzgam Railway, Panzgam, Agriculture areas will be affected from 11:00 AM to 04:00 PM on 29 January, 2025.

Similarly, to carry out Balance works for augmentation of conductor for SIDCO feeder and evacuation of power from GIS Lassipora (Bay 6), the shutdown of below given 33KV lines shall be observed.

The shutdown of Lassipora-Pulwama Line shall be observed due to which 33/11KV Receiving Stations at Pulwama, Pinglena, Tenghar, Covid Hospital and Flour Mill shall remain off while power supply to the Pulwama A,B,C,D Babhar, Pinglena and Tenghar areas will be affected from 10:00 AM to 04:30 PM on 01 & 09 February, 2025.

Also, the shutdown of 33KV Lassipora-Landoora Line shall be observed due to which 33/11KV Receiving Stations at Landoora and Moomin shall remain off while power supply to the Landoora, Hajipora, Hermain, Mantribugh, Chakoora and Moomain areas will be affected from 10:00 AM to 04:30 PM on 01 & 09 February, 2025.

Further, the shutdown of 33KV Lassipora-Reshipora Line shall be observed due to which 33/11KV Receiving Station at Reshipora shall remain off while power supply to the Zainapora, Nagbal, Reban and Aglar areas will be affected from 10:00 AM to 04:30 PM on 01 & 09 February, 2025.

Moreover, the shutdown of 33KV Lassipora-Keegam Mitrigam Line shall be observed due to which 33/11KV Receiving Stations at Mitrigam, Keegam, Gulshanabad and Charipora shall remain off while power supply to the Murran, Rahmoo, Gulshanabad and Mitrigam areas will be affected from 10:00 AM to 04:30 PM on 01 & 09 February, 2025.

Also, the shutdown of 33KV Lassipora-Lassipora Line shall be observed due to which 33/11KV Receiving Station at Lassipora shall remain off while power supply to the Arihal, Achan, Lassipora, Odoora and Ahgam will be affected from 10:00 AM to 04:30 PM on 01 & 09 February, 2025.

Similarly, to carry out temporary shifting and permanent raising of Sopore Tap Line near Lalad Amargarh, the shutdown of Delina-Sopore Line shall be observed due to which 33/11KV Receiving Station at Sopore-II shall remain off while power supply to the Sopore Town, Amargarh, Krankshivan Colony and adjoining areas will be affected from 10:00 AM to 04:00 PM on 29 January, 2025.

Also to carry out Augmentation of 0.1 ACSR to 0.2 ACSR of NehalporaMarkundal Line, the shutdown of Nehalpora-Markundal Line shall be observed due to which 33/11KV Receiving Stations at Markundal, Naidkhai, Shahgund and Aglar shall remain off while power supply to the Naidkhai, Markundal, Sumbal, Ankhul, Gundboon and adjoining areas will be affected from 10:00 AM to 03:00 PM on 29 January and 01 February, 2025.

The shutdown of Delina-Amargarh Ckt-I shall be observed due to which power supply to the Rohama, Chakloo, Watergam, Hachipora, Hadipora, Sidiq Colony, Sopore Town, Nowpora, Seelo, Achabal, Bomai, Arampora, Sher Colony, Panzipora, Watlab, Bugoo, Tujjar Sharief, Dooru, Seer, Tangdhar, Keran, Kralpora, Panzgam, Trehgam, Chowkibal, Hyhama, Karihama, Magam, Krusen, Vilgam, Sogam, Machil, Tikker, Drugmulla, Handwara, Pohrupeth, Zachaldara, Chajmulla and Safalpora areas will be affected from 11:00 AM to 03:00 PM on 28 January, 2025.

Further, to carry out Augmentation of 33KV Budgam – Parthan Line, the shutdown of 33KV Waterhail tap Line shall be observed due to which 33/11KV Receiving Station at Waterhail shall remain off while power supply to the Samsaan, Parthan, Waterhail PHE Substation will be affected from 10:00 AM to 04:00 PM on 30 January and 04 & 06 February, 2025.