Srinagar, May 02: Power Controller Kashmir has informed that, the power supply to Receiving Station Gopalpora shall remain affected due to facilitate pending stringing of 33 Kv Kanganhal Line on May 04 and 06 from 10.00 am to 4 pm.
Similarly, in order to facilitate augmentation of 33 Kv Lisser- Hiller line the power supply to receiving stations Shankarpora, Hiller and Arkashipora shall remain affected on May 04 and 07 from 10 am to 4 pm.
Likewise, the power supply to receiving stations Delina, Sopore-2 and Jetty shall remain affected on May 06, 09 and 15 from 10 am to 4 pm due to carry out the stabilization work.
Similarly, in order to facilitate re-conductoring works the power supply to receiving stations Baramulla-1, Kanilbagh, Baramulla-2, Drangbal, Bagi-i-Islam and Sheeri shall remain affected on May 04 from 9 am to 3 pm.
Likewise, to carry out branch cuttings/ pruning of tress laying in 33 Kv lines, the power supply shall remain affected to receiving station Kathidarwaza on May 6 and 9; receiving stations Lalbazar and Baghwanpora on May 6; receiving stations Foodpark, Khunmoh Phase-III Khunmoh Phase-I on May 07; Cement Plants (Khyber, SAIFCO and TCI Max) on May 07 and 13; receiving stations Khunmoh Old, Balhama, Wuyan, TCI Old, and Covid Hospital on May 10 and receiving stations Badamibagh, Sonwar, Panthachowk, Tanganar WWS, Govt Pres, Lasjan and DPS from 10 am to 5 pm. (GNS)